The Railway Board had approved setting up of Gati Shakti Units (GSUs) in all Divisions of Indian Railways during July 2022 to fast track the construction works required to remove bottlenecks in operations and improve mobility that would lead to increase cargo loading. Accordingly, a Gati Shakti unit is formed in NED Division and is established in 1st floor of DRM Office Complex of Rail Vikas Sadan.
Later on, in the month of August 2024 Railway Board has decided to reorganise Gati Shakti Units in divisions. Subsequently, Gati Shakti Units in SCR zone have been reorganised and Gati Shakti Units of Hyderabad and Nanded Divisions have been merged into Single unit under CPM/GS/II/SC.
Divisional Gati Shakti Unit shall be responsible for planning and execution of following works:
1.Carrying out feasibility study followed by preparation of Detailed Project Report for further consideration of the Railway Board.
2.Station Redevelopment.
3.Plan Head 53: Customer Amenities.
4.Plan Head 16: Traffic Facilities.
5.Plan Head 29: Road Safety and level crossing.
6.Plan Head 30: Road Under Bridge (RUB) and Road Over Bridge (ROB).
7.Plan Head 33: Signal and Telecommunication such as EI, RRI including in private siding.
8.Plan Head 36: Provision of Escalator and lifts.
9.Plan Head 42: Workshop including production unit work.
10. All siding works and deposit work.
11.Electrification of sidings, workshops & small leftover RE patches.
12.All coal connectivity projects/port connectivity works under different Plan Head (confined within the divisional boundary).
|
Details of staff working in Gati Shakti – Nanded Division |
||
|
S.NO |
Name (Sri/Smt.) |
Designation |
|
1 |
Ladi Sambasiva Rao |
Chief Project Manager/GS/II/SC |
|
2 |
Md. Nuruddin Abid |
Dy.Chief Engineer/GS/NED |
|
3 |
Vacant |
ADEN/GS/NED |
|
4 |
Pramod Kumar |
SSE/Drg/GS/NED |
|
5 |
Suman Kumar |
SSE/W/GS/ADB |
|
6 |
Brijesh Kumar |
SSE/W/GS/AWB |
|
7 |
Ashutosh Singh Yadav |
SSE/W/GS/NED |
|
8 |
Jadhav Milind Dhondiba |
JE/Drg/GS/NED |
|
9 |
Wankar Vivek Rajhans |
JE/Drg/GS/NED |
|
10 |
Samala Ravalika |
Sr.Stenographer/GS/NED |
Works allotted and Progress
|
Plan Head |
No of works allotted |
Total Value in Rs. |
|
PH 1500 (Doubling ) |
1 |
72.34 cr |
|
PH 1600 (Traffic Facility) |
3 |
37.989 cr |
|
PH 3000 (ROB/RUB) |
3 |
147.760 cr |
|
PH 4200 (Workshop) |
2 |
53.08 cr |
|
PH 5300 (Passenger Amenities) |
14 |
242.8099 cr |
|
Total |
23 |
553.9789 cr |
Status / Progress of works
|
PH 1500 (DOUBLING ) |
||||
|
S. No. |
Name of work |
Year of Sanction |
Estimated Cost |
Present Status |
|
1 |
PURNA- BY PASS LINE -- Bypass line at Purna Jn. station (3.22 km) for connecting Purna-Akola & Purna-Secunderabad (PB#34/CR/2023-24). |
2023-24 |
72.34 cr |
Process for land acquisition in progress |
|
PH 1600 (Traffic Facility) |
||||||||||
|
S. No. |
Name of work |
Year of Sanction |
Estimated Cost |
Present Status |
||||||
|
1 |
Gevrai - New crossing station of standard layout (two loop lines) at GEVRAI between Badnapur-Karmad stations (19.47 kms) in J-AWB section. |
2023-24 |
Rs. 28.374 cr |
Loop line /Temp diversion work in progress. |
||||||
|
2 |
MALTEKDI:- Conducting Techno-Feasibility study and preparation of DPR for the work of " Development of Coaching Depot in MTDI Yard in connection with Decongestion of NED Yard" |
2024-25 |
Rs.0.50 cr |
TCP UNDER PROCESS |
||||||
|
3 |
MTDI-Proposal for extension of shunting neck (CSR-80m) and make stable line of CSR-720m towards Nanded end at Maltekadi station. |
2022-23 |
Rs.9.1156 cr |
Commissioned April 2024 |
||||||
|
PH 5300 (Passenger Amenities) |
||||||||||
|
1 |
Appointment of technical consultation for techno-economic feasibility studies for re-development of Nanded Railway station. |
2022-23 |
Rs. 0.6882 cr |
Estimate submitted to Railway Board. |
||||||
|
2 |
Technical consultancy for feasible studies for redevelopment under "Amrit Bharat station scheme" of 15 stations in NED Division. |
2022-23 |
Rs 1.50 Cr |
Feasible studies under progress. |
||||||
|
3 |
Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at PBN Station. |
2023-24 |
Rs 7.898 Cr |
Station Building phase -1 in progress |
||||||
|
4 |
Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at Purna Station. |
2023-24 |
Rs 7.4758 Cr |
Station Building on PF 1 in progress |
||||||
|
5 |
NED DIv :- Proposed construction of FOBs at Nagarsol , Parbhani, Hingoli, Washim and Adilabad Stations in Amrit Bharat Stations Scheme. |
2023-24 |
Rs 40.82 Cr |
Nagarsol- Girder launching completed,Parbhani, Hingoli, Washim, Adilabad foundation work in progress |
||||||
|
6 |
Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at HNL Station. |
2023-24 |
Rs 5.175 Cr |
Work in progress |
||||||
|
7 |
Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at MUE Station. |
2023-24 |
Rs 4.0527 Cr |
Work in progress |
||||||
|
8 |
Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at GNH Station. |
2023-24 |
Rs 5.4877 Cr |
Work yet to be started |
||||||
|
9 |
GS/NED: MUE, KNVT & GNH : Provision of 12m wide Foot Over Bridges with Ramp under Amrit Bharat Station Scheme. |
2023-24 |
Rs 33.531 Cr |
MUE- Girder launching in progress, KNVT- Girder launching completed. & GNH |
||||||
|
10 |
GS/NED: PTU, SELU & PAU : Provision of 12m wide Foot Over Bridges with Ramp under Amrit Bharat Station Scheme. |
2023-24 |
Rs 33.529 Cr |
PTU- Launching completed, SELU- foundation in progress girder reached at site & PAU – foundation work in progress |
||||||
|
11 |
Dinegaon :- Proposed Goods lines & Platform for handling goods loading/unloading facilities (Phase-1) |
2023-24 |
Rs 22.8494 Cr |
Work in progress. |
||||||
|
12 |
Development of new goods loading /unloading facilities at Karmad (KMV) station including Land acquisition |
2024-25 |
Rs 47.3896 Cr |
Estimate sanctioned. Tender open on 21.09.2025. |
||||||
|
13 |
Extension of Cover Over Platform so as to cover the entire remaining length of all platforms at Parbhani, Purna and Mudkhed stations. |
2024-25 |
Rs 18.8135 Cr |
Estimate prepared, waiting for S&T estimate. |
||||||
|
14 |
Tensile fabrics roof over Porch&Parking ,Precast RCC Coping on PF,Ducts on PF&Solar Panels over Parking roof top at MUE,PAU,PBN,HNL,GNH& New BO at HNL |
2024-25 |
Rs 13.60 Cr |
Estimate under preparation. |
||||||
|
|
|
|
|
|
||||||
|
PH 3000 (ROB/RUB works) |
||||||||||
|
S. No |
PB No. |
Name of work |
Year of Sanction |
Present Status |
||||||
|
1 |
116 |
NED: MUE-PMKT: Construction of 2-lane ROB in lieu of LC No.29 at Km 159/9-160/0 between Umram- Adilabad stations and LHS in lieu of LC No.30 at Km 161/2-3 near Adilabad Yard |
2016-17 |
Revised Detailed sanction for 100% railway funding. |
||||||
|
2 |
105 |
Aurangabad - Chikalthana - MMR-MUE Section: - Proposed construction of RUB in lieu of Manned LC No 55 @ km 117/6-7 between AWB-CTH Station. |
2021-22 |
Work completed. |
||||||
|
3 |
110 |
NED DIv :-MMR-MUE Section :- Proposed RUB Bridge No 185A as 1X5.00X3.00 M pre-cast RCC BOX @ KM 159/2-3 in between BDU-J stations. |
2022-23 |
Work completed |
||||||
|
10 |
111 |
GSU - Conducting feasibility study, investigation, Detailed Survey for Construction of ROB/RUBs in lieu of 17 LCs. |
2023-24 |
DPR work in progress |
||||||
|
PH 4200 (Workshop work) |
||||
|
S. No. |
Name of work |
Year of Sanction |
Estimated Cost |
Present Status |
|
1 |
ADB- Construction of new pit line CAMTECH design of 24 coach length |
2021-22 |
Rs. 22.2776cr |
Works nearing completion |
|
2 |
AWB- Construction of CAMTECH design new pit line of 16 coach length at Aurangabad (AWB) station of NED division |
2022-23 |
Rs 30.81 |
Works nearing completion |
|
Station Redevelopment Works |
||
|
S. No. |
Name of work |
Present Status |
|
1 |
NED Station - Redevelopment of station |
|
|
List of Stations selected under “Amrit Bharat Station Scheme” - NED Div |
||
|
S.No |
Name of the station |
Total Cost (Crs) |
|
1 |
Nagarsol |
|
|
2 |
ROTEGAON |
|
|
3 |
PURTUR |
|
|
4 |
SELU |
|
|
5 |
MANWAT ROAD |
|
|
6 |
PARBHANI |
|
|
7 |
PURNA |
|
|
8 |
MUDKHED |
|
|
9 |
BHOKAR |
|
|
10 |
HIMAYATNAGER |
|
|
11 |
KINWAT |
|
|
12 |
ADILABAD |
|
|
13 |
HINGOLI |
|
|
14 |
WASHIM |
|
|
15 |
GANGAKHER |
|
|
List of stations where 12 meter Foot Over Bridge Proposed |
|
|
Sl. No. |
Name of the station |
|
1 |
NAGARSOL |
|
2 |
PARTUR |
|
3 |
SELU |
|
4 |
PARBHANI |
|
5 |
PURNA |
|
6 |
MUDKHED |
|
7 |
KINWAT |
|
8 |
ADILABAD |
|
9 |
HINGOLI |
|
10 |
WASHIM |
|
11 |
GANGAKHER |
|
List of LC gate where feasibility study is in progress for proving Road Over Bridge/ Road Under Bridge |
|||
|
Sl. No. |
LC No. |
LC Location |
Between Station |
|
MANMAD – MUDKHED Section |
|||
|
1 |
52 |
112/700-800 |
AURANGABAD YARD |
|
2 |
53 |
114/300-400 |
AURANGABAD (AWB)- CHIKALTHAN (CTH) |
|
3 |
56 |
120/900-121/000 |
|
|
4 |
69 |
153/600-700 |
KARMAD(KMV) – Badnapur(BDU) |
|
5 |
76 |
174/200-300 |
BADNAPUR(BDU)- JALNA(J) |
|
6 |
77 |
174/800-900 |
|
|
7 |
82 |
184/00-100 |
JALNA(J)- SARWADI(SVD) |
|
8 |
118 |
287/200-300 |
PERGAON (PG) – PARBHANI (PBN) |
|
9 |
119 |
288/300-400 |
PERGAON (PG) – PARBHANI (PBN) |
|
10 |
120 |
289/400-500 |
PERGAON (PG) – PARBHANI (PBN) |
|
11 |
121 |
289/900- 290/00 |
PERGAON (PG) – PARBHANI (PBN) |
|
12 |
125 |
299/800-900 |
PARBHANI(PBN)- PINGLI (PIZ) |
|
13 |
129 |
305/700-800 |
PINGLI(PIZ) – MIRKHEL(MQL) |
|
PRLI VAIJNATH – PARBHANI |
|||
|
14 |
1 |
330/600-700 |
PARBHANI(PBN) – POKARNI NARSIMBHA(PKNS) |
|
15 |
3 |
324/700-800 |
|
|
MUDKHED - ADILABAD |
|||
|
16 |
5 |
38/800-900 |
BOKHAR(BOKR) – HADGAON ROAD(HDGR) |
|
PURNA – AKOLA |
|||
|
17 |
102 |
796/400-500 |
AMANWADI (AMW) – JAULKA(JUK) |