Gatishakti NED


GATI SHAKTI UNIT

NANDED DIVISION

SOUTH CENTRAL RAILWAY


The Railway Board had approved setting up of Gati Shakti Units (GSUs) in all Divisions of Indian Railways during July 2022 to fast track the construction works required to remove bottlenecks in operations and improve mobility that would lead to increase cargo loading. Accordingly, a Gati Shakti unit is formed in NED Division and is established in 1st floor of DRM Office Complex of Rail Vikas Sadan.

Later on, in the month of August 2024 Railway Board has decided to reorganise Gati Shakti Units in divisions. Subsequently, Gati Shakti Units in SCR zone have been reorganised and Gati Shakti Units of Hyderabad and Nanded Divisions have been merged into Single unit under CPM/GS/II/SC.

Divisional Gati Shakti Unit shall be responsible for planning and execution of following works:

1.Carrying out feasibility study followed by preparation of Detailed Project Report for further consideration of the Railway Board.

2.Station Redevelopment.

3.Plan Head 53: Customer Amenities.

4.Plan Head 16: Traffic Facilities.

5.Plan Head 29: Road Safety and level crossing.

6.Plan Head 30: Road Under Bridge (RUB) and Road Over Bridge (ROB).

7.Plan Head 33: Signal and Telecommunication such as EI, RRI including in private siding.

8.Plan Head 36: Provision of Escalator and lifts.

9.Plan Head 42: Workshop including production unit work.

10. All siding works and deposit work.

11.Electrification of sidings, workshops & small leftover RE patches.

12.All coal connectivity projects/port connectivity works under different Plan Head (confined within the divisional boundary).

 

Details of staff working in Gati Shakti – Nanded Division

S.NO

Name

(Sri/Smt.)

Designation

1

Ladi Sambasiva Rao

Chief Project Manager/GS/II/SC

2

Md. Nuruddin Abid

Dy.Chief Engineer/GS/NED

3

Vacant

ADEN/GS/NED

4

Pramod Kumar

SSE/Drg/GS/NED

5

Suman Kumar

SSE/W/GS/ADB

6

Brijesh Kumar

SSE/W/GS/AWB

7

Ashutosh Singh Yadav

SSE/W/GS/NED

8

Jadhav Milind Dhondiba

JE/Drg/GS/NED

9

Wankar Vivek Rajhans

JE/Drg/GS/NED

10

Samala Ravalika

Sr.Stenographer/GS/NED


 

Works allotted and Progress

 

Plan Head

No of works allotted

Total Value in Rs.

PH 1500 (Doubling )

1

72.34 cr

PH 1600 (Traffic Facility)

3

37.989 cr

PH 3000 (ROB/RUB)

3

147.760 cr

PH 4200 (Workshop)

2

53.08 cr

PH 5300 (Passenger Amenities)

14

242.8099 cr

Total

23

553.9789 cr



Status / Progress of works

 

PH 1500 (DOUBLING )

S. No.

Name of work

Year of Sanction

Estimated Cost

Present Status

1

PURNA- BY PASS LINE -- Bypass line at Purna Jn. station (3.22 km) for connecting Purna-Akola & Purna-Secunderabad (PB#34/CR/2023-24).

2023-24

72.34 cr

Process for land acquisition in progress

 

PH 1600 (Traffic Facility)

S. No.

Name of work

Year of Sanction

Estimated Cost

Present Status

1

Gevrai - New crossing station of standard layout (two loop lines) at GEVRAI between Badnapur-Karmad stations (19.47 kms) in J-AWB section.

2023-24

Rs. 28.374 cr

Loop line /Temp diversion work in progress.

2

MALTEKDI:- Conducting Techno-Feasibility study and preparation of DPR for the work of " Development of Coaching Depot in MTDI Yard in connection with Decongestion of NED Yard"

2024-25

Rs.0.50 cr

TCP UNDER PROCESS

3

MTDI-Proposal for extension of shunting neck (CSR-80m) and make stable line of CSR-720m towards Nanded end at Maltekadi station.

2022-23

Rs.9.1156 cr

Commissioned April 2024

PH 5300 (Passenger Amenities)

1

Appointment of technical consultation for techno-economic feasibility studies for re-development of Nanded Railway station.

2022-23

Rs. 0.6882 cr

Estimate submitted to Railway Board.

2

Technical consultancy for feasible studies for redevelopment under "Amrit Bharat station scheme" of 15 stations in NED Division.

2022-23

Rs 1.50 Cr

Feasible studies under progress.

3

Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at PBN Station.

2023-24

Rs 7.898 Cr

Station Building phase -1 in progress

4

Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at Purna Station.

2023-24

Rs 7.4758 Cr

Station Building on PF 1 in progress

5

NED DIv :- Proposed construction of FOBs at Nagarsol , Parbhani, Hingoli, Washim and Adilabad Stations in Amrit Bharat Stations Scheme.

2023-24

Rs 40.82 Cr

Nagarsol- Girder launching completed,Parbhani, Hingoli, Washim, Adilabad foundation work in progress

6

Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at HNL Station.

2023-24

Rs 5.175 Cr

Work in progress

7

Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at MUE Station.

2023-24

Rs 4.0527 Cr

Work in progress

8

Improvements/Development to Station building, Toilets, Facade, Circulating area etc., at GNH Station.

2023-24

Rs 5.4877 Cr

Work yet to be started

9

GS/NED: MUE, KNVT & GNH : Provision of 12m wide Foot Over Bridges with Ramp under Amrit Bharat Station Scheme.

2023-24

Rs 33.531 Cr

MUE- Girder launching in progress, KNVT- Girder launching completed. & GNH

10

GS/NED: PTU, SELU & PAU : Provision of 12m wide Foot Over Bridges with Ramp under Amrit Bharat Station Scheme.

2023-24

Rs 33.529 Cr

PTU- Launching completed, SELU- foundation in progress girder reached at site & PAU – foundation work in progress

11

Dinegaon :- Proposed Goods lines & Platform for handling goods loading/unloading facilities (Phase-1)

2023-24

Rs 22.8494 Cr

Work in progress.

12

Development of new goods loading /unloading facilities at Karmad (KMV) station including Land acquisition

2024-25

Rs 47.3896 Cr

Estimate sanctioned. Tender open on 21.09.2025.

13

Extension of Cover Over Platform so as to cover the entire remaining length of all platforms at Parbhani, Purna and Mudkhed stations.

2024-25

Rs 18.8135 Cr

Estimate prepared, waiting for S&T estimate.

14

Tensile fabrics roof over Porch&Parking ,Precast RCC Coping on PF,Ducts on PF&Solar Panels over Parking roof top at MUE,PAU,PBN,HNL,GNH& New BO at HNL

2024-25

Rs 13.60 Cr

Estimate under preparation.

 

 

 

 

 

 

 

 

PH 3000 (ROB/RUB works)

S. No

PB No.

Name of work

Year of Sanction

Present Status

1

116

NED: MUE-PMKT: Construction of 2-lane ROB in lieu of LC No.29 at Km 159/9-160/0 between Umram- Adilabad stations and LHS in lieu of LC No.30 at Km 161/2-3 near Adilabad Yard

2016-17

Revised Detailed sanction for 100% railway funding.

2

105

Aurangabad - Chikalthana - MMR-MUE Section: - Proposed construction of RUB in lieu of Manned LC No 55 @ km 117/6-7 between AWB-CTH Station.

2021-22

Work completed.

3

110

NED DIv :-MMR-MUE Section :- Proposed RUB Bridge No 185A as 1X5.00X3.00 M pre-cast RCC BOX @ KM 159/2-3 in between BDU-J stations.

2022-23

Work completed

10

111

GSU - Conducting feasibility study, investigation, Detailed Survey for Construction of ROB/RUBs in lieu of 17 LCs.

2023-24

DPR work in progress

                     



PH 4200 (Workshop work)

S.

No.

Name of work

Year of Sanction

Estimated Cost

Present Status

1

ADB- Construction of new pit line CAMTECH design of 24 coach length

2021-22

Rs. 22.2776cr

Works nearing completion

2

AWB- Construction of CAMTECH design new pit line of 16 coach length at Aurangabad (AWB) station of NED division

2022-23

Rs 30.81

Works nearing completion

 

Station Redevelopment Works

S.

No.

Name of work

Present Status

1

NED Station - Redevelopment of station

  • IDPR submitted to Railway Board.



List of Stations selected under “Amrit Bharat Station Scheme” - NED Div

S.No

Name of the station

Total Cost

(Crs)

1

Nagarsol

 

2

ROTEGAON

 

3

PURTUR

 

4

SELU

 

5

MANWAT ROAD

 

6

PARBHANI

 

7

PURNA

 

8

MUDKHED

 

9

BHOKAR

 

10

HIMAYATNAGER

 

11

KINWAT

 

12

ADILABAD

 

13

HINGOLI

 

14

WASHIM

 

15

GANGAKHER

 

 

List of stations where 12 meter Foot Over Bridge Proposed

Sl. No.

Name of the station

1

NAGARSOL

2

PARTUR

3

SELU

4

PARBHANI

5

PURNA

6

MUDKHED

7

KINWAT

8

ADILABAD

9

HINGOLI

10

WASHIM

11

GANGAKHER

 

List of LC gate where feasibility study is in progress for proving Road Over Bridge/ Road Under Bridge

Sl. No.

LC No.

LC Location

Between Station

MANMAD – MUDKHED Section

1

52

112/700-800

AURANGABAD YARD

2

53

114/300-400

AURANGABAD (AWB)- CHIKALTHAN (CTH)

3

56

120/900-121/000

4

69

153/600-700

KARMAD(KMV) – Badnapur(BDU)

5

76

174/200-300

BADNAPUR(BDU)- JALNA(J)

6

77

174/800-900

7

82

184/00-100

JALNA(J)- SARWADI(SVD)

8

118

287/200-300

PERGAON (PG) – PARBHANI (PBN)

9

119

288/300-400

PERGAON (PG) – PARBHANI (PBN)

10

120

289/400-500

PERGAON (PG) – PARBHANI (PBN)

11

121

289/900- 290/00

PERGAON (PG) – PARBHANI (PBN)

12

125

299/800-900

PARBHANI(PBN)- PINGLI (PIZ)

13

129

305/700-800

PINGLI(PIZ) – MIRKHEL(MQL)

PRLI VAIJNATH – PARBHANI

14

1

330/600-700

PARBHANI(PBN) – POKARNI NARSIMBHA(PKNS)

15

3

324/700-800

MUDKHED - ADILABAD

16

5

38/800-900

BOKHAR(BOKR) – HADGAON ROAD(HDGR)

PURNA – AKOLA

17

102

796/400-500

AMANWADI (AMW) – JAULKA(JUK)