South Central Railway enhances Speed to 130 Kmph
Along the Golden Quadrilateral & Golden Diagonal sections
A total of 2824 Kms (including Up & Down Lines)
over the Zone is now fit to run at 130 Kmph speed
South Central Railway has started the New Year by achieving a landmark achievement by drastically enhancing the maximum speed to 130 kmph for 1,280 km length out of 1,612 Km in Golden Quadrilateral - Golden Diagonal (GQ-GD) route.This covers the entire GQ-GD route over SCR, except Vijayawada - Duvvada section, where signaling up-gradation work is in progress.
The enhanced speed limits could be achieved due to the systematic and planned strengthening of track & its infrastructure by removing bottlenecks in these sections on a fast pace. This included heavier rails, laying of 260 meters Long welded rail panels, improvement of curves and gradients among others. The Zone has utilized the opportunity of the Lockdown period and low train movement last year (due to the COVID-19 pandemic) to complete all necessary infrastructure up-gradation works.
Based on these improvements done by the Zone, the RDSO/Lucknow conducted oscillation trials through Confirmatory Oscillograph Car Run (COCR) consisting of instrumented coaches of all classes at 130 Kmph speed during July and October last year. During this check, in addition to track parameters, other areas like Signaling aspect, Traction distribution equipment, Locomotive & coach fitness were also checked and recorded.
Accordingly, the zone has received sanction to enhance the maximum speed limits to 130 kmph along the following routes:
1.Golden Diagonal (Grand Trunk) Route: 744 Route Km
i.Ballarshah to Kazipet – 234 Rkm
ii.Kazipet-Vijayawada-Gudur– 510 Rkm
2.Golden Quadrilateral Route (Chennai -Mumbai section): 536 Route Km
i.Renigunta to Gooty - 281 Rkm
ii.Gooty to Wadi - 255 Rkm
Already, the maximum speed limits in the High-Density Network (HDN) between Secunderabad – Kazipet (132 Kms distance) had been enhanced to 130 kmph. As such, including both the Up and Down lines in these sections, a total of 2,824 kms (1412Rkms)has now been made fit to run at a speed of 130 kmph. This covers the entire GQ-GD route over SCR, except Vijayawada - Duvvada section, where signaling up-gradation work is in progress.
Shri Gajanan Mallya, General Manager, SCR has specially congratulated all the Officials and staff who have put their strenuous efforts in completing all the required aspects in these sections. He also said that though pandemic situation is prevailing across the globe, the staff and officersof the Zone have relentlessly worked as team to complete the targeted work. He opined that the enhancement of speed in these important sections of Golden Quadrilateral/Golden Diagonal and high density routes will help in smooth operation of train services.He also stated that the running time of the passenger services will be considerably reduced and pave the way for running more number of trains.