Salient features:
1. | Total Area of Workshop | 27.50 Hectares |
2. | Covered Area | 5.40 Hectares |
3. | Rail track length | 8.25 kms |
4. | Machinery & Plants | 551 nos. |
5. | Railway Quarters | 584 nos. |
6. | Budget Grant 2021-22 (Workshop Manufacturing Suspension) | Figs. In Crores | Mechanical | Electrical |
Net Debits | 253.14 | 68.38 |
Net Credits | 252.74 | 67.71 |
Total | 558. 77 | 136.09 |
7. | Targets 2021-22 | Periodic Overhauling (POH) of Coaches | IntermediateOverhauling (IOH) of bogies |
1550 Nos. | ICF | LHB |
2464 | 576 |
8. | Average Monthly Power consumption in KWH | Grid | 58202 |
Solar | 49097 |
9. | Manpower as on 01.06.2021. (Mech. + Elec.) | Department | Sanctioned | Actual | Vacancies |
Mechanical | 2666 | 2152 | 514 |
Electrical | 632 | 484 | 148 |
Total | 3298 | 2636 | 662 |
| | | | | | | |
Present activities of the Workshop:
1. Periodic Overhauling (POH) of Air Conditioned & Non Air Conditioned Broad Gauge ICF/LHB Designed coaches.
2. Intermediate Overhauling (IOH) of ICF Designed Conventional and LHB designed FIAT Bogies.
3. POH of DEMU,EMU/MEMU Power & Trailer cars & SPART coaches
4. POH of Tower cars(4W & 8W)
5. POH of Defense owned and camping coaches
6. Supply of Wheel sets, Distributor Valves (DVs) & Bogie Mounted Brake Cylinders (BMBCs) to divisions.
7. LOFP/SC: Assembly and Supply of Lube oil & Fuel oil filters of Diesel Locomotive to all over Indian Railway.
8.RBK/Yadgir: Manufacturing of LHB Bogie frames.